Praterm

Heat Plant Address

32-500 Chrzanów
ul. Pogorska 36
tel. +48 32 623 51 04
fax. +48 32 623 52 54
email: pec_chrzanow@praterm.pl


Po polsku     English version


Current
temperature:
4.1 °C



Boiler house

HP in Chrzanów is equipped with:
  • Ciepłownia "Południe" installed capacity 87,2 MW
    • 3 coal boilers WR-25
  • Ciepłownia "Śląska" installed capacity 29,1 MW
    • 2 coal boilers WR-10
    • 1 coal boiler WR-5
  • Two local boiler houses
    • ul. Focha 1 - capacity 0,514 MW using coal
    • ul. Rospontowa 16 - capacity 0,780 MW - using gas
HP in Trzebini is equipped with:
  • oil-gas boiler house with installed capacity of 1,4 MW
  • oil-gas boiler house with installed capacity of 0,68 MW
HP in Libiąż is equipped with:
  • HP "Flagówka" - installed capacity 17,4 MW
  • 6 coal boilers WR 2,5 MW
Grid

The system consists of 40,1 km pipes with a total volume of 5647 m3. There are 218 heat transformers connected to the grid.

Efficiency

Currently, the production efficiency of main boiler houses is close to 78%. The investments planned for 2004 and 2005 will increase this ratio up to 83%. The HP consumes 43,000 tons of coal, 324,000m3 of gas and 6,000 MWh of electricity.

    Copyright© Dalkia term 2002-2010 email: info@dalkiaterm.pl